Planning Completeness and Project Definition

Repeated County incompleteness findings, unresolved administrative transitions, and project-definition issues.

AnalysisSource linked

Executive summary

Amador County repeatedly found the application incomplete—in March 2022, June 2023, and September 2025. The supplied record then shows an April 24, 2026 referral for another completeness review on May 7, followed by a May 27 referral that had advanced to CEQA review and draft Conditions of Approval. The supplied files do not yet contain a clear written completeness determination explaining that transition.

SourceMarch 23, 2022 deficiency notice

Planning required a detailed to-scale site plan, building specifications, landscape/water information, parking and circulation, phasing/max buildout, and official water availability.

Open source record

2023 requirements

The June 22, 2023 final deficiency notice was much more detailed. It required grave plans, well/setback information, soil-storage locations, parking/ADA information, funerary preparation details, equipment/material storage, a cemetery-specific soils/hydrology/hydrogeology suitability study, a General Plan Amendment, and potentially mineral studies.

SourceJune 22, 2023 deficiency notice

The letter says the MRZ General Plan designation was inconsistent with the proposed cemetery and required a General Plan Amendment.

Open source record

2025 incompleteness finding

TAC again found the application incomplete on September 18, 2025. The September 29 letter required an engineer/surveyor-quality preliminary plan, sewage-disposal feasibility work, equipment/fuel storage information, operating details, and removal of stale building references so the application would be internally consistent.

SourceSeptember 29, 2025 deficiency notice

The letter describes the minimum information required before another TAC completeness review.

Open source record

2026 transition

The April 24, 2026 packet still says TAC will review the application for completeness on May 7. By May 27, Planning states TAC will review the project application and CEQA Initial Study and make recommendations on the environmental document, project, and draft Conditions of Approval to the Planning Commission.

SourceMay 7, 2026 TAC packet

The April 24 referral describes the May 7 meeting as a completeness review.

Open source record

SourceMay 27, 2026 referral

The later referral describes a CEQA/project recommendation stage.

Open source record

Open question

What written determination, staff memo, or TAC action established that the application had become complete, and how were the 2023 and 2025 deficiencies resolved or modified?

General Plan designation

The 2023 deficiency notice says the MRZ designation is inconsistent with the cemetery and requires a General Plan Amendment. Yet the current 2026 referral still identifies the parcel as MRZ. No General Plan Amendment application was located in the supplied current application packet. That is a documentation question, not proof that no amendment exists elsewhere.

SourceJune 22, 2023 deficiency notice

Planning identified MRZ as inconsistent and recommended OR/Open Recreation among the possible consistent designations.

Open source record

SourceMay 27, 2026 referral

The current County referral still lists the General Plan designation as MRZ.

Open source record