Executive summary
On November 24, 2026, land-use and environmental consultant Peggy Flynn, representing Amador Data Center Community Action, sent Amador County Planning a technical submission concerning the proposed Buena Vista Data Center at 4655 Coal Mine Road. The email requests inclusion in the project file, distribution to reviewers, acknowledgment and future meeting and environmental-review notices. The group reports that the application was filed November 19 and understands that initial Technical Advisory Committee (TAC) consideration and formal CEQA review had not begun.
The submission requests a whole-project assessment of the proposed data center, existing biomass generation, new gas turbines, battery storage, cooling, water systems and site disturbance. Its 101 numbered issues are requests for evidence, not findings of significant impact or permit violations.
Source: Submission, p. 1; November 24 email; Submission, p. 3.
What this record establishes
Documented: The content and date of a community technical submission and its transmittal.
Attributed: Application descriptions, historical records, industry statements and legal interpretations quoted or summarized in the submission.
Not established: County acceptance or response, actual contamination, underground voids beneath the development, a violation, a final CEQA pathway or project approval. The archive has not independently reviewed every underlying source.
Project scope and power
The submission describes a 14.4 MW data center tied to an existing biomass plant described as 18.5 MW, three proposed 6 MW gas turbines, and a 10 MW / 20 MWh battery energy storage system. It cites an approximately 54-acre parcel and a lease area of 30.396 acres, plus an easement area of approximately 9.82 acres. It requests a reconciled equipment schedule, operating modes, land boundaries and a complete list of permits.
| Component | Reported rating | Question raised |
|---|---|---|
| Data center | 14.4 MW | IT load versus total facility demand |
| Biomass plant | 18.5 MW | Net output, downtime, restart and auxiliary loads |
| Gas turbines | 3 × 6 MW | Operating hours, emissions and backup role |
| Battery | 10 MW / 20 MWh | Supported loads, dispatch and duration |
Archive analysis: At the stated 10 MW power rating, the battery cannot alone supply a 14.4 MW load. Dividing 20 MWh by 14.4 MW gives an energy-only estimate of roughly 1.4 hours, not a feasible discharge at that power rating. At 10 MW, 20 MWh corresponds to two hours ideally, before losses or usable-capacity constraints. Actual design and dispatch are unknown.
The group also requests clarification of earlier public references to phased development (about 5 MW then 15 MW) and possible larger biomass/pyrolysis concepts, because the current application reportedly says there are no development phases or associated projects. Those earlier concepts do not establish future commitments.
Source: Submission, p. 4; Submission, p. 5; Submission, p. 8.
Historical mining and industrial activity
The memorandum cites 1915 and 1927 State Mineralogist reports describing underground lignite mining in the area, including shafts and drifts. A 1954 report describes lignite strip mining. The group asks for a records-based geotechnical investigation to determine whether underground workings were removed, filled or remain, and whether they intersect proposed structures or utilities. Historic descriptions and mineral reservations do not establish that voids exist beneath the lease area.
The submission also cites Central Valley Regional Water Board Order R5-2011-0009 for a history of wax production beginning in 1946, solvent extraction beginning in 1950, and a cogeneration facility built in 1986. It requests existing site investigations and characterization where warranted, particularly for soil disturbance, construction dust, dewatering, runoff and reuse or disposal of excavated materials. Historical groundwater data and waste-management records are not equivalent to a finding of a current release.
Source: Submission, p. 11; Submission, p. 12; Submission, p. 13; Submission, p. 14; Submission, p. 15.
Reported restart delays and pipeline leaks
The submission cites an October 29, 2026 2CRSi release attributing a biomass recommissioning delay to pipeline leaks reported by NYGC. It asks for the affected systems, contents, repair and acceptance-testing records, and whether any release was reported. The reported leak is not itself evidence of environmental contamination. Current operating status and the original supporting records remain open questions.
Source: Submission, p. 3 (PD-04); Submission, p. 27 (reference P18).
Water, wetlands, flood risk and wastewater
The consultant requests a seasonal and drought-period water balance for all connected operations, evidence supporting atmospheric water generator yield, and clarification of sanitary and process wastewater. The plans reportedly identify wetlands, an existing well, a leachfield and an evaporation pond. The submission asks whether the pond is the regulated Class II impoundment, whether new waste streams would enter it, and whether existing monitoring and permits remain applicable.
It also asks for a current floodplain determination and equipment elevations because turbines and a new gas line are shown near the approximate FEMA Zone A boundary. The location and jurisdiction of wetlands and actual flood exposure require technical confirmation.
Source: Submission, p. 9; Submission, p. 10; Submission, p. 16.
Air emissions, noise and emergency services
Requested studies include combined emissions from the biomass plant and turbines, construction dust, greenhouse-gas accounting, low-frequency and tonal noise, vibration, fire and battery hazards, emergency access, fire-water capacity, evacuation, staffing and traffic. The submission asks that operating modes, including outages and concurrent equipment, be evaluated consistently rather than relying only on normal-operation assumptions.
Source: Submission, p. 8; Submission, p. 10; Submission, p. 16; Submission, p. 17.
Prior approvals and California environmental review
The group asks the County to identify operative biomass approvals, amendments, conditions, mitigation and current compliance evidence; compare the proposed project against prior approvals; and explain how adopted General Plan mitigation programs apply. It requests a supported decision on the appropriate California Environmental Quality Act (CEQA) pathway, not a determination based only on an application fee category.
The submission identifies seven 2026 data-center statutes (SB 887, AB 2469, AB 1577, AB 2619, SB 886, AB 2383 and SB 1168), with a stated effective date of January 1, 2027. It asks County Counsel to determine the applicability of each law to this application and later decisions. The archive has not independently verified enactment, effective dates, thresholds or applicability; this section reports the group's request, not a legal conclusion.
Source: Submission, p. 5; Submission, p. 6; Submission, p. 7; Submission, p. 8.
Timeline
Advance technical submission sent
Transmittal asks for placement in the project file and advance distribution. No acknowledgment supplied.
Application reportedly filed
Filing date reported in the submission; official receipt and completeness determination not supplied.
Industry statement cited
Submission cites a partner statement about biomass restart delays (P18; underlying record not independently reviewed).
101 investigation requests
Appendix A assigns unique IDs to the requests. Appendix B asks for comparisons with prior approvals; Appendix C defines operating scenarios; Appendix D indexes 55 cited sources; Appendix E explains the need and feasibility of the proposed studies. The searchable tracker reproduces all 101 Appendix A rows with the source page, subject, cited basis and requested action. It does not imply that any request has been accepted or that a study is legally required.
Source: Submission, p. 19; Submission, p. 24; Submission, p. 25; Submission, p. 31.
Questions remaining and records to obtain
- Complete application, drawings, receipt and completeness status, agency referrals and TAC schedule.
- Operative prior approvals and environmental documents, current Water Board and Air District permits, inspections and monitoring records.
- Actual biomass operating status, pipeline repair and testing records, electrical balance and equipment schedule.
- Site investigations, mine maps, grading plans, wastewater and fire-response studies, and any consultant scopes.
- County response to the submission and eventual environmental-review pathway, including legal applicability analysis.
These are potential archival follow-ups, not representations that records are missing from the County file.
Source and publication notes
The report is based on the supplied November 24 email and its matching PDF attachment. The PDF is a community submission, not an official County finding or independent site assessment. Its 55 cited sources are indexed in Appendix D; they have not all been obtained or verified by the archive. The public PDF preserves all 33 pages and visible content; incidental document metadata was removed. The email is a readable archival derivative with the phone number and technical routing headers omitted; the sender's name and listed email contacts are retained. Originals remain separate from the public derivatives.