UP-26;11-2 · November 24, 2026

Environmental review issue tracker

Search all 101 project clarification and investigation requests from Appendix A. These are community requests, not verified findings or County commitments.

Tracking status

Every issue is marked “Response not in archive” because the supplied materials contain no County acknowledgment or disposition. This is not a claim that the County has failed to respond. Source basis codes refer to Appendix D in the submission, not independently verified archive records. Open source index.

101 of 101 requests

Issue / subjectCited basisRequested actionStatus / source
PD-01Whole undertaking / phasesProject descriptionP1 EIF 9–10,28; P19; P20Reconcile shared systems, dependencies and future development.Response not in archivePDF p. 19
PD-02Equipment / footprintProject descriptionP1 plans/descriptionMaster equipment schedule and all permanent/temporary/off-site work.Response not in archivePDF p. 19
PD-03Internal consistencyProject descriptionP1 forms/plansResolve staffing, capacity, area, APN and drawing differences against originals.Response not in archivePDF p. 19
PD-04Plant status / baselineProject descriptionP6 finding 5; P18Operating history, restart status, reported pipeline leaks and repairs.Response not in archivePDF p. 19
PD-05CoolingProject descriptionP1 cover; EIF 5, 23Technology, fluids (incl. PFAS), refrigerants, equipment location.Response not in archivePDF p. 19
PD-06Existing featuresProject descriptionP1 EIF 2; S1.0/S1.1Features removed, relocated, protected or reused.Response not in archivePDF p. 19
PD-07Approvals listProject descriptionP1 EIF; P29Complete list of required permits and approvals (15124(d)).Response not in archivePDF p. 19
LU-01Parcels / rightsLand use and propertyP1 consent/deed; P6 finding 2Full APN/lot/lease/easement crosswalk and authority map.Response not in archivePDF p. 19
LU-02CompatibilityLand use and propertyP1 zoning/settingAdopted map/policy/finding and sensitive-use compatibility review.Response not in archivePDF p. 19
LU-03Adjacent usesLand use and propertyP1 S1.0; P14 D-1(a)(9)Rancheria, casino/hotel, residences, farmland and contracts.Response not in archivePDF p. 19
HC-01Approval recordPrior approvals and complianceP1 existing-facility relianceOperative environmental/approval chain and approved plans.Response not in archivePDF p. 19
HC-02CompliancePrior approvals and compliancePrior permits requestedCurrent condition/monitoring evidence and accountable entities.Response not in archivePDF p. 19
HC-03ConformityPrior approvals and complianceP1 new proposalReasoned current-project/approved-project comparison.Response not in archivePDF p. 19
GP-01GP mitigation crosswalkGeneral PlanP11; P12; P14 p. P-2; P15– P17Relied-upon programs, status and project-level application.Response not in archivePDF p. 19
GP-02Program D-1 criteriaGeneral PlanP14 pp. P-15–P-19Address applicable D-1(a) criteria expressly.Response not in archivePDF p. 19
GP-03Adopted textGeneral PlanP11; P12; P13Certified Attachments 1–2 to Res. 16-115 and Sept. 21, 2016 errata.Response not in archivePDF p. 19
GP-04Fiscal / public serviceGeneral PlanP14 D-1(a)(7)Fiscal and public-service evaluation.Response not in archivePDF p. 19
CE-01Review pathwayCEQA and review processP1 fee worksheet; P2/P4Confirm status and supported CEQA framework, not billing category.Response not in archivePDF p. 19
CE-02BaselineCEQA and review processP1 operations; P6 historyActual conditions, source activity, field dates and rationale.Response not in archivePDF p. 19
CE-03Independent reviewCEQA and review processP5Scopes, County direction/review, peer review and lawful cost recovery.Response not in archivePDF p. 19
CE-04New state lawsCEQA and review processP31–P37Law-by-law trigger/date/threshold/exception analysis.Response not in archivePDF p. 20
CE-05Early consultationCEQA and review processP29Responsible/trustee and expert agencies; tribes.Response not in archivePDF p. 20
CE-06Prior agreementsCEQA and review processP29Disclose any agreements; confirm no commitment.Response not in archivePDF p. 20
CE-07Need / feasibilityCEQA and review processP38–P40Reasons by ID where a request is declined.Response not in archivePDF p. 20
EN-01Power balanceEnergy and electricityP1 cover/EIF27Gross/net and IT/total load, station service, charging and losses.Response not in archivePDF p. 20
EN-02Reliability / backupEnergy and electricityP1 equipmentAvailability, battery role, dispatch, shedding and failure scenarios.Response not in archivePDF p. 20
EN-03Grid rightsEnergy and electricityP1 export claimService/import/export/interconnection and upgrade footprint.Response not in archivePDF p. 20
EN-04Energy analysisEnergy and electricityP1; P33Appendix F/G analysis; Gov. Code 65909.3 estimates.Response not in archivePDF p. 20
AQ-01TurbinesAir qualityP1 EIF21,25,27Specifications, emissions/modes/controls and enforceable hours.Response not in archivePDF p. 20
AQ-02ExposureAir qualityP1 combined operationsConstruction/operation/cumulative air and health-risk analysis as warranted.Response not in archivePDF p. 20
AQ-03Biomass fuelAir qualityP1 plant relianceConsistent throughput/moisture/specification and dust/ash/odor accounting.Response not in archivePDF p. 20
AQ-04Construction dustAir qualityP1 EIF 21Dust controls; dust as contaminant pathway where warranted.Response not in archivePDF p. 20
GH-01GHG / benefitsGreenhouse gasesP1 coverActual-system inventory and supported lifecycle/credit assumptions.Response not in archivePDF p. 20
WR-01Total waterWater and wastewaterP1 EIF5–6,26,29Existing/restart/incremental/total seasonal supply- demand balance.Response not in archivePDF p. 20
WR-02Atmospheric waterWater and wastewaterP1 coverLocal yield, ratings, energy, treatment, storage and contingency.Response not in archivePDF p. 20
WR-03WastewaterWater and wastewaterP1 services; P6 findings6–9Sanitary/process/residuals/capacity/permit reconciliation.Response not in archivePDF p. 20
WR-04Existing wellWater and wastewaterP1 S1.1; P6 B.2Type, status and proposed use/protection/destruction.Response not in archivePDF p. 20
WR-05Septic / leachfieldWater and wastewaterP1; S1.0; P14 D-1(a)(5)System capacity, combined load and avoidance.Response not in archivePDF p. 20
WR-06Statutory water informationWater and wastewaterP32; P34WSA and Bus. & Prof. Code 16100.4 information.Response not in archivePDF p. 20
WD-01Pond / monitoring networkWaste discharge and impoundmentP1 Ascent figure; P6; P9Identify pond; map monitoring features and setbacks.Response not in archivePDF p. 20
WD-02New flows to impoundmentWaste discharge and impoundmentP6; Water Code 13260Any new flows; material-change determination.Response not in archivePDF p. 20
WD-03Discharger / transferWaste discharge and impoundmentP6 E.7Current discharger/operator; transfer request.Response not in archivePDF p. 20
WD-04Compliance recordWaste discharge and impoundmentP10Monitoring, compliance and enforcement records.Response not in archivePDF p. 20
NV-01Combined acousticsNoise and vibrationP1 EIF23Representative baseline, spectra, receptor model and combined modes.Response not in archivePDF p. 21
NV-02Low-frequency / tonalNoise and vibrationP1 equipment; P3; P49; P50Supported frequency/tonal methods and criteria beyond dBA as warranted.Response not in archivePDF p. 21
NV-03VibrationNoise and vibrationP1 work/equipment; P11 p. 33Groundborne screening/analysis distinct from airborne sound.Response not in archivePDF p. 21
NV-04Acoustic verificationNoise and vibrationP1 assurances; P47; P48Commissioning/worst-mode tests, monitoring and correction.Response not in archivePDF p. 21
BIO-01Species/habitatBiological resourcesP1 EIF29–30Qualified current screening, field/seasonal surveys as indicated.Response not in archivePDF p. 21
BIO-02Elderberry/beetleBiological resourcesP1 EIF29; P28Shrub identification, habitat/potential and supported avoidance.Response not in archivePDF p. 21
BIO-03Wetlands/watersBiological resourcesP1 plans/EIF29; P27Delineation, jurisdiction and full disturbance/hydrology overlay.Response not in archivePDF p. 21
BIO-04Indirect effectsBiological resourcesP1 settingLight/noise/dust/water/corridor effects and controls.Response not in archivePDF p. 21
BIO-05Streambed alterationBiological resourcesP1 S1.1; EIF 29Fish and Game Code 1602 evaluation; herbicide use.Response not in archivePDF p. 21
CR-01Cultural/tribalCultural and tribal resourcesP1 EIF29Records, actual disturbance, surveys, consultation and protected information.Response not in archivePDF p. 21
CR-02Tribal consultationCultural and tribal resourcesP1 S1.0PRC 21080.3.1 consultation before document preparation.Response not in archivePDF p. 21
CR-03Industrial historyCultural and tribal resourcesP6 finding 3Evaluate processing remnants as potential historical resources.Response not in archivePDF p. 21
GS-01Soils/miningGeology and miningP1 EIF24,29–31; deed; P11 p. 27Geotechnical and documented workings/subsidence/fill assessment.Response not in archivePDF p. 21
GS-02FillGeology and miningP1 EIF 24, 29Extent and composition of fill.Response not in archivePDF p. 21
GS-03Acid-generating potentialGeology and miningP6 Table 1Test before reuse or stockpiling (hypothesis).Response not in archivePDF p. 21
GS-04Corrosivity / soil gasGeology and miningP6Sulfate, corrosivity, methane and CO2.Response not in archivePDF p. 21
GS-05Historical underground workingsGeology and miningP1 item 31; P6; P53–P55; P14 D-8, D-9Map workings vs. all structures; backfill/removal status; void investigation if unresolved.Response not in archivePDF p. 21
MIN-01Mineral classificationMineral resourcesP22; P14 D-1(a)(13)Classification, designation, PRC 2762(d).Response not in archivePDF p. 21
MIN-02Mineral estatesMineral resourcesP1 deed/titleHolders and surface-entry rights.Response not in archivePDF p. 21
HZ-01Historical hazardsHazardous materialsP6 findings2–6Existing contamination investigations and full site-use reconstruction.Response not in archivePDF p. 21
HZ-02Investigation coverageHazardous materialsP6 pp.1–5; Sec. 13.2–13.3Inventory prior investigations and map locations/depths/analytes vs all disturbance; identify reliable conclusions and gaps.Response not in archivePDF p. 21
HZ-03Pathways / conceptual modelHazardous materialsP6 findings14,16–17,21; Sec. 13.4Evaluate project-created/exacerbated dust, vapor, runoff, dewatering, trench and haul pathways with receptor evidence.Response not in archivePDF p. 22
HZ-04Characterization / timingHazardous materialsSec. 13.5/13.7; P7Where warranted obtain qualified sampling/QA/QC sufficient for significance/mitigation before the relevant decision; do not replace essential analysis with a generic future plan.Response not in archivePDF p. 22
HZ-05Agency / containment coordinationHazardous materialsP6 B/E; P8; Sec. 13.6Current WDR/MRP, release/integrity/compliance/assurance records; Water Board coordination and warranted additional oversight.Response not in archivePDF p. 22
HZ-06Operational hazardous materialsHazardous materialsP1 descriptionInventory incl. coolants/PFAS; containment.Response not in archivePDF p. 22
HZ-07Building materialsHazardous materialsP1 S1.1ACM, lead paint, PCB surveys; NESHAP.Response not in archivePDF p. 22
HZ-08Pipeline leaksHazardous materialsP18Include in hazards baseline.Response not in archivePDF p. 22
HZ-09Cortese / P-14Hazardous materialsP11 p. 28; P14List check; apply P-14 and D-9.Response not in archivePDF p. 22
MW-01CharacterizationExcavated material and wasteP1 EIF 17, 20; P23Pre-disturbance characterization of waste streams.Response not in archivePDF p. 22
MW-02Earthwork quantitiesExcavated material and wasteP1 EIF 17Cut/fill/import/export; on-site balancing.Response not in archivePDF p. 22
MW-03Classification frameworkExcavated material and wasteP23; P24RCRA/California-only/DOT/acceptance distinctions.Response not in archivePDF p. 22
MW-04Management planExcavated material and wasteP41; P42Soil and Materials Management Plan with action levels.Response not in archivePDF p. 22
MW-05Worker protectionExcavated material and waste8 CCR 3203, 5192IIPP and, where applicable, HAZWOPER plan.Response not in archivePDF p. 22
MW-06CEQA treatmentExcavated material and wasteP7No substitution of disposal compliance for impact analysis.Response not in archivePDF p. 22
MW-07Destination facilitiesExcavated material and wasteP11 section 2.9.1Current authorization and acceptance.Response not in archivePDF p. 22
MW-08RecordsExcavated material and wasteP1Data, manifests, tickets; closeout reconciliation.Response not in archivePDF p. 22
HY-01FloodingHydrology and floodingP1 descriptionCurrent map/elevation/hydraulics/equipment and access assessment.Response not in archivePDF p. 22
HY-02Drainage/gradingHydrology and floodingP1 EIF17,22; P6 BCut/fill, runoff, dewatering, pond catchment and spill pathways.Response not in archivePDF p. 22
HY-03Floodplain sitingHydrology and floodingP1 S1.0; P6; P14 D-1(a)(11)Floodplain determination and equipment elevations.Response not in archivePDF p. 22
HY-04Construction stormwaterHydrology and floodingP25; P26; P14 D-5CGP coverage, risk level, non-visible pollutant sampling.Response not in archivePDF p. 22
HY-05DewateringHydrology and floodingP6Testing, treatment and disposal.Response not in archivePDF p. 22
HY-06Industrial stormwaterHydrology and floodingP10IGP coverage for new facilities.Response not in archivePDF p. 22
FR-01BESS/gasFire and emergency responseP1 EIF25–26; P45; P46Testing, scenarios, separation/isolation and engineering safeguards.Response not in archivePDF p. 23
FR-02Response capacityFire and emergency responseP1 shared fire systemsFlow, access, evacuation, response, training and public upgrades.Response not in archivePDF p. 23
FR-03Response standardFire and emergency responseP14 P-6, D-1(a)(3); P1 EIF 26Applicable standard, source and site-specific capability.Response not in archivePDF p. 23
FR-04Evacuation / wildfireFire and emergency responseP11 section 3.6.1; P14Apply P-12 and D-10.Response not in archivePDF p. 23
FR-05Fire-water lineFire and emergency responseP1 S1.1Protect, relocate and test line and hydrant.Response not in archivePDF p. 23
TR-01Construction/staffingTraffic and constructionP1 EIF4,8,14Logistics, trips, parking, VMT and shift reconciliation.Response not in archivePDF p. 23
TR-02Roads / fuel tripsTraffic and constructionP1 connected operationsRoutes, bridges, safety/cumulative/evacuation and prior duties.Response not in archivePDF p. 23
TR-03Heavy loadsTraffic and constructionP1 equipmentCoal Mine Road access and structures for deliveries.Response not in archivePDF p. 23
AE-01Visual/lightingAesthetics and lightingP1 EIF18–19Sensitive views, elevations, photometrics and screening.Response not in archivePDF p. 23
UT-01Utilities/wasteUtilities and wasteP1 EIF20–22,26Service/extension footprints and construction/maintenance/end-of-life waste.Response not in archivePDF p. 23
UT-02Operational wasteUtilities and wasteP1 EIF 20E-waste, battery modules, filters, coolant.Response not in archivePDF p. 23
UT-03DecommissioningUtilities and wasteP1Plan and financial assurance.Response not in archivePDF p. 23
OT-01Other checklist topicsOther checklist topicsP1 settingSupported agriculture/forestry/minerals/recreation/population screening.Response not in archivePDF p. 23
CU-01CumulativeCumulative effectsP1 EIF9–10,28Actual connected/future scope and resource-specific cumulative projects.Response not in archivePDF p. 23
AL-01AlternativesAlternativesP1 proposalIf EIR: reasonable lower-impact options, no project and exclusions.Response not in archivePDF p. 23
MM-01Mitigation/responsibilityMitigation and responsibilityP1 indemnity; P6 D/E; P7Enforceable performance, successors, verification and lawful assurance.Response not in archivePDF p. 23